§ 201-4. Evaluation procedure.


Latest version.
  • A. 
    If an environmental impact statement is required in accordance with the first above-mentioned stipulation(s) herein, it shall be submitted to the Secretary of the Planning Board 60 days prior to filing for final approval of the site plan.
    B. 
    Upon receipt of the application, the Secretary of the Planning Board shall forward the environmental impact statement to the Environmental Commission and to any other Borough agency which the Planning Board may desire for consultation.
    C. 
    Such aforementioned Borough agency or agencies shall review the applicant's environmental impact statement and shall report their findings and comments within 30 days of the date of submission to the Planning Board.
    D. 
    The Planning Board and/or the Environmental Commission may require the opinion of experts in its review of the environmental impact statement and, if deemed essential, may hire an expert consultant to assist it in the evaluation of submitted information by the applicant.
    E. 
    Fees for the costs of such consultant as described in Subsection D above shall be paid by the applicant.
    F. 
    Copies of the environmental impact statement shall be on file and available for inspection in the office of the Construction Official of the Borough of Bellmawr.